| S. No. |
Work Name |
A/A & E/S (Rs.in Lacs) |
Date of Start |
Target Date of Completion |
Expected Date of Completion |
% Progress |
Remarks |
| Amount |
Date |
|
| 1. |
Construction of District Office Complex, South District at Hauz Rani, New Delhi |
12.46 Crore |
04-11-2004 |
|
|
|
|
The client dept. directed not to start construction till revised
estimate of Rs. 16 Crore (Due to new site) is approved by Divisional Commissioner /EFC
|
| 2. |
C/o Pucca School Building for Govt. School at Gazipur |
493.85 Lacs |
|
01-02-2005 |
31-11-2006 |
|
100% |
Completed |
| 3. |
C/o Old Age Home at Pocket-14, Sec-8, Dwarka |
167.13 Lacs |
|
04-03-2006 |
03-06-2007 |
|
60% |
|
| 4. |
C/o Old Age Home at Bindapur |
246.40 Lacs |
|
09-09-2006 |
08-11-2007 |
|
25% |
|