Project Cost Estimates


Land Acquisition Cost
The total project area is 1865 acres. (755 Ha.) 740 acres in Bhawana village has been acquired @ Rs. 7.33 lakhs/acre and Rs. 10,000 per acre has been paid towards compensation for structures. For the same land an enhanced compensation and solatium has also been paid @ Rs. 7.76 lakhs/acre amounting to rs. 56.76 crores, resulting in a total cost of Rs. 112.48 crores.

The break-up of land cost by area is given below :

(Cost figures in Rs. Crores)
Land Area740 Acres324 Acres800 Acres
Cost54.9848.75161.00
Structure Compensation0.74--
Enhanced Compensation56.76--
Total112.4848.75161.00

Cost of land acquired ( March 1998 ) : 161.23 Rs. Crores
Cost of land to be acquired ( Septrmber 2000) : 161.00 Rs. Crores

Services

The anticipated cost for provision of various services at current price level in the industrial area is given below.

DescriptionCost in Rs. Crores
Power288
Roads162
Water Supply100
Sewerage64
Storm Water Management58
Solid WAste Management7
Fire Fighting1
Horticulture & landscaping8
Services Building12
Pre-opreative Expenses 5
Total705